Project ID |
Description |
Approval Y or N |
Recommended Amt. |
Comments |
Status |
| 1. Green Power Switch Purchase |
Green Power can be purchased in any amount as a one time
purchase. |
Yes |
$1,500 |
A one time purchase does not require a contract. The committee
has already voted for a minimum one time purchase from the
first years funds. |
Complete |
| 2. Electric Vehicle |
Purchase 2 electric vehicles @$13,000 each for non license
or licensed use on campus. Identify with logos indicating "TTU
Student Sustainability Fees at Work" or similar student
identification. |
Yes |
$26,000 |
UT purchased 1 and now has purchased 3 more with very good
success. Maintenance would implement. |
1 purchased |
| 2. Addenda |
Electric panels would be installed where visible. Typically,
roof mounting rather than at ground level. |
Yes |
$15,000 |
Add solar panels for charging batteries on electric vehicles
with offsetting load of charger. |
|
| 3. Intramural Field Light Replacement |
Replace the outdated, inefficient incandescent light fixtures
on a portion, SE Field, of the south Intramural Field. Matching
Funds supplied by the Intramural Program for replacing fixtures
and panels per TVA Recommendations. Infrastructure supported
by Cookeville Electric Dept. |
Yes |
$40,000 |
Deferred Maintenance Project. TBR Regional Designers would
provide drawings. Maintenace and hourly contract labor would
implement. |
Complete |
| 4. Residence Hall Steam Valve Replacement |
Connect the buildings heating system steam valve to the Building
Automation System for automatically adjusting the temperature
to the changing outdoor conditions. This measure would decrease
the coal boiler load and provide the occupants with a more
comfortable building. |
Yes |
$20,000 |
Deferred maintenance project. Funding allows the students
to win with environmental and comfort benefits. Maintenance
would implement by connecting the valves to the Building Automation
System. |
Complete |
| 5. Biodiesel Equipment Conversion |
Buy biodiesel from Harris Oil, local provider. Convert Generators
to biodiesel(B20) by modifying Title V Air Pollution Permit.
Catepillar does not require engine modifications. |
Yes |
$10,000 |
Utilize TBR Regional Designer for modifying Title V Air Pollution
Permit. |
Complete |
Recommended Total Amount
|
$112,500 |
Leave the remainder for contingency. |